Demo by Drop In Labs · shown for a sample company with illustrative rates · no contact details are collected · settings and jobs cannot be changed here

Assumptions

The numbers that are not product data and not prices: waste, offcut pairing, screws per sheet, sealant per m². Sorted so the guesses come first. The back-test on your past jobs is what should set these; you can also set them from experience.

ItemValueUnitStatusWhere the number comes from
pairing tri
Offcut pairing allowance on triangular planes. Real practice orders to length and pairs offcuts across mirrored planes. First thing to calibrate. LIKELY OVERLAPS waste_hip: raked cuts are most of the waste on a hip roof, so applying both probably double counts. The back-test decides which carries the loss.
factorassumed
guess: none
pairing trap
Offcut pairing allowance on trapezoidal planes. Second thing to calibrate. Same overlap with waste_hip as pairing_tri.
factorassumed
guess: none
rip waste flag fraction
Flag a rectangular plane when more than this fraction of the last sheet is ripped off.
fraction of a sheetassumed
guess: none
batten extra
Allowance on batten length for valleys, plane changes and penetrations.
fractionassumed
guess: none
anticon extra
Allowance on blanket area beyond the 150 mm tab already handled by the 1050 effective cover.
fractionassumed
guess: none
clip wastefractionassumed
guess: none
clips per sheet per support
Concealed-fix profiles. Confirm with Lysaght.
eaassumed
guess: Not published anywhere found
screws per clip
Concealed-fix profiles.
eaassumed
guess: none
sealant m2 per tube simplem2assumed
guess: Practitioner allowance, no source
sealant m2 per tube complexm2assumed
guess: Practitioner allowance, no source
dp catchment m2 default
Should come from BoM rainfall intensity for the site and AS/NZS 3500.3. Overridable per job.
m2assumed
guess: none
skip count tile
Tiles are ~45 kg/m2 against metal ~4.5.
eaassumed
guess: none
skip count metaleaassumed
guess: none
qbcc base
Replace with the live table.
AUDassumed
guess: Linear approximation of the published alterations premium table
qbcc rate
Replace with the live table.
fractionassumed
guess: Linear approximation of the published alterations premium table
zincalume factor
Applied to sheet, cappings and rainwater goods when the customer chooses ZINCALUME.
factorassumed
guess: Retail listings show unpainted ZINCALUME about 10 to 20% under COLORBOND Classic
waste gable
Simple gable.
fractionassumed
convention: AU trade convention; sheets are cut to length so waste is far below US shingle figures
waste hip
Hipped. Applied on top of the pairing allowances, which probably double counts; see pairing_tri.
fractionassumed
convention: AU trade convention
waste skillion
Single plane.
fractionassumed
convention: AU trade convention
waste complex
Cut-up roofs: valleys present or four or more penetrations.
fractionassumed
convention: AU trade convention, 12 to 15 percent
sheet length rounding m
Sheet lengths ordered to the next 50 mm.
massumed
convention: Supplier ordering practice
batten screws per crossing
Batten to rafter fixings at each crossing.
eaassumed
convention: Trade practice
rafter spacing m
Used only to count batten fixings. Confirm on site.
massumed
convention: Typical QLD domestic truss spacing
mesh extrafractionassumed
convention: AS/NZS 4389 side laps not less than 150 mm plus end ties
capping lap allowance
Applied to ridge, hip and barge capping.
factorassumed
convention: Trade practice: 100 to 150 mm laps. Lysaght does not publish it.
screw waste
Dropped, stripped and mis-driven screws.
fractionassumed
convention: Trade practice
sheet gutter allowance m
Added to every sheet length.
massumed
published: NCC 2022 HP 7.2: sheets overhang the fascia by not less than 50 mm
anticon roll width mmassumed
published: CSR Bradford Anticon
anticon effective cover m
Using 1200 instead of 1050 under-orders by 12.5 percent.
massumed
published: CSR Bradford Anticon installation guide: 150 mm foil overlap tab
valley gutter projection m
Per valley end.
massumed
published: NCC 2022 HP 7.2: valley projects not less than 150 mm into the eaves gutter
gutter max m per downpipemassumed
published: NCC 2022 HP 7.4
qbcc threshold inc gstAUDassumed
published: QBCC home warranty insurance is mandatory over $3,300 incl GST